GMC high-voltage electrostatic precipitator; Installation requirement 1: Conduct pre installation inspection and acceptance of the lower platform foundation of the dust collector. Install the various components of the electrostatic precipitator according to the requirements of the "Installation Manual for Electrostatic precipitator" and design drawings. Based on the confirmed acceptance foundation, establish the center installation benchmark for the electrostatic precipitator and use it as the installation benchmark for the anode cathode system.
Installation requirements for GMC high-voltage electrostatic precipitator II: Check the flatness, column spacing, and diagonal error of the foundation plane.
GMC high-voltage electrostatic precipitator installation requirements three: Check the shell components, correct any transportation deformation, and install layer by layer from bottom, such as support group - bottom beam (install ash hopper and internal platform of electric field after inspection) - column and side wall panel - top beam - inlet and outlet (including distribution board and groove board) - anode and cathode system - top cover plate - high-voltage power supply and other equipment.
The GMC high-voltage electrostatic precipitator ladder, platform, and railing can be installed layer by layer according to the installation sequence. After each layer is installed, it must be inspected and recorded according to the requirements of the "Electrostatic precipitator installation manual" and design drawings, such as flatness, diagonal, column spacing, perpendicularity, pole spacing, etc. After installation, the equipment should be checked for tightness, and any welding gaps should be repaired.